River Poddle FAS - Ground Investigation Contract

River Poddle FAS - Ground Investigation Contract

By poddleadmin
Wednesday, 16th October 2019
Filed under: News

As part of the proposed River Poddle Flood Alleviation Scheme, the Ground Investigation contract for the scheme will commence on the 17th October in various locations along the River Poddle from Tymon Park to St Martins Drive in Kimmage. Works will commence in Tymon Park with all works expected to take 3-4 weeks.

Ground Investigation consists of of taking soil samples and determining the location of underground sevices by the use of Boreholes, Trial Pits and Slit Trenches. As most of the works will be carried out in public parks, grass verges, footpaths and roads, pedestrian and traffic management will be put in place to accomodate the works where required so we ask all park, road and footpath users to follow all relevant site signage. We thank you in advance for your patience while the works are on-going and for any distruption that may be caused.

Please email info@poddlefas.ie if you have any enquiries.

Work Locations from 17/10 - 23/10 are as follows;

17/10/19 - Tymon Park North and Tymon Park - Trial Pits and Slit Trenches

Tymon North Park - Adjacent to Tymon Castle site

Tymon North Park - Adjacent to ESB Substation

Tymon Park - North Western side of Tymon Lakes 

Tymon Park - North Eastern side of Tymon Lakes

18/10/19 - Tymon Park - Trial Pits and Slit Trenches

Tymon Park - North East of Tymon Lakes at Pedestrian bridge

Tymon Park - Eastern Footpath at Tymon Lakes

Tymon Park - South side of river adjacent to Osprey Lawn

22/10/19 - Open space between Whitehall Park and Grosvenor - Trial Pits and Slit Trenches

23/10/19 - Tymon Park and Wainsfort Manor Cresent - Trial Pits and Borehole

Tymon North Park - Adjacent to Tymon Castle Site

Wainsfort Manor Cresent - Open space

Wainsfort Manor Cresent - Adjacent to Lakelands Overflow